Worthington roads are under construction
The following is an update on city of Worthington street construction sites:By: Daily Globe, Worthington Daily Globe
The following is an update on city of Worthington street construction sites:
Roos Avenue (Diagonal Road to Winifred Street): Bituminous pavement reconstruction delayed to a tentative beginning of July 6.
Alley Block 12 (Third Avenue to Fourth Avenue):
Bituminous pavement reconstruction (Delayed to a tentative beginning of July 8.
Marine Avenue (Clary Street to Oxford Street): Spot curb and gutter repairs in progress; began Thursday. Bituminous pavement work tentatively beginning July 12.
Strait Avenue (Clary Street to Miller Street): Concrete pavement restoration began Monday.
First Avenue (13th Street through 15th Street): Concrete pavement restoration began Tuesday.