Worthington street construction

The following is an update on city of Worthington street construction sites:

By: DAILY GLOBE, Worthington Daily Globe

The following is an update on city of Worthington street construction sites:

Roos Avenue (Diagonal Road to Winifred Street): Bituminous pavement reconstruction. Bituminous paving completed Thursday; project substantially complete.

Alley Block 12 (Third Avenue to Fourth Avenue): Bituminous pavement reconstruction of Alley behind City Hall. In progress; began July 8. Bituminous paving tentatively scheduled for Monday.

Marine Avenue (Clary Street to Oxford Street): Spot curb and gutter repairs. Spot curb and gutter in progress; began June 24. Again delayed to a new tentative beginning; bituminous pavement reconstruction tentatively set to start July 26. Bituminous paving and overlay will be at a later date in late July or early August.

First Avenue (13th Street through 15th Street): Concrete pavement restoration. In progress; began June 29.

Clary Street (Church Avenue to Humiston Avenue): In progress; began Thursday. Bituminous overlaid concrete pavement restoration

Alley Block 30 (Seventh Avenue to Eighth Avenue): Bituminous pavement reconstruction (alley behind Television Service Center and Johnson Eye Clinic). In progress; began Tuesday. Bituminous paving tentatively scheduled for Monday.