Construction update

The following is an update on City of Worthington construction sites:

The following is an update on City of Worthington construction sites:

Marine Avenue (Clary Street to Oxford Street): Bituminous paving and overlay began Aug. 5 and was to be completed Aug. 6.

Clary Street (Church Avenue to Humiston Avenue): Bituminous overlaid concrete pavement restoration began July 15 and is in progress.

11th Street (Clary Street to East Ninth Avenue): Sanitary sewer spot repairs began Aug. 4 and is in progress.

U.S. 59 (Humiston Avenue), Ryan’s Road and Ray Drive: U.S. 59 median work began Aug. 2 and is in progress.

Humiston Avenue at Clary Street: Concrete pavement restoration was postponed and is now slated to begin Monday.

First Avenue (10th Street through 11th Street): Concrete pavement reconstruction began Aug. 2 and is in progress.