Lewis and Clark awards pump station, meter building contract

TEA, S.D. -- Lewis and Clark Regional Water System's Board of Directors Monday awarded a $3,616,200 contract to Gridor Construction, Buffalo, Minn., that includes three components -- a pump station, meter building and pumps. The pump station will...

TEA, S.D. -- Lewis and Clark Regional Water System’s Board of Directors Monday awarded a $3,616,200 contract to Gridor Construction, Buffalo, Minn., that includes three components -- a pump station, meter building and pumps. The pump station will be located five and a half miles south of Luverne and the meter building, which serves as a connection point for Lincoln-Pipestone Rural Water System, will be located three miles east of Adrian.

In addition, the contract includes adding pumps at the existing pump station/meter building along the Iowa-Minnesota border, which serves as a connection point for both Rock Rapids and Rock County Rural Water District. The substantial completion deadline for construction is November 2017.

“The low bid was $200,000 less than originally budgeted, which is important as it relates to our federal funding ceiling, so we were pleased with the results,” said Executive Director Troy Larson. Gridor is currently constructing meter buildings for Lewis and Clark near Crooks and Madison.

What To Read Next
The North Dakota Highway Patrol investigated the Wednesday, Jan. 25, crash.
Fundraising is underway to move the giant ball of twine from the Highland, Wisconsin, home of creator James Frank Kotera, who died last month at age 75, 44 years after starting the big ball.
“We see that when things happen in the coastal areas, a few years later, they start trending toward the Midwest,” said Rep. Ben Krohmer, serving his first term in the House.
“This is sensationalism at its finest, and it does not deserve to be heard in our state capitol,” Rep. Erin Healy, a Democrat and one of 10 votes against the bill in the 70-person chamber, said.