I-90 construction from Beaver Creek to South Dakota starts June 3

Entire project to continue to November.

road-stock-unsplash.jpg
Road Stock Art (Muhammed Owsama/Unsplash)
We are part of The Trust Project.

MANKATO — Weather permitting, construction on eastbound and westbound Interstate 90 from east of Beaver Creek to the South Dakota border will begin, according to the Minnesota Department of Transportation.

During the first stage of construction, traffic will be reduced to a single lane in each direction in the westbound lanes. The eastbound on and off ramps at Minnesota 23 will be closed. The eastbound Beaver Creek Rest Area located west of the South Dakota border will also be closed during this stage. Travel information will be available at the eastbound Adrian Rest Area. This first stage of construction is anticipated to last until early August.

During the second stage of construction, traffic will be reduced to a single lane in each direction in the eastbound lanes from the South Dakota border to Rock County 11. Construction will require on and off ramp closures on westbound I-90 at Minnesota 23 during this stage. On and off ramp closures will also be required at Rock County 6 for approximately one week for paving. The timing of the one-week ramp closures is yet to be determined, however, the ramps will be open during the annual Sturgis Motorcycle Rally.

During the final stage of construction, traffic will be reduced to one lane in each direction from the South Dakota border to east of Luverne.

Construction on I-90 is expected to be complete in November, weather permitting. The project includes a concrete pavement overlay on the eastbound and westbound lanes and reconstruction of shoulders. The project also includes the extension of outside ramp shoulders for truck parking, guardrail repair and improved drainage with the cleaning, repair and replacement of culverts and pipes.

ADVERTISEMENT

For more information, visit dot.state.mn.us/d7/projects/i90sd-luverne/index.html.

Duininck, Inc. was awarded the project with a bid of $22,483,064.90.

What To Read Next
Three individuals were sentenced recently in Nobles County Fifth District Courts in cases previously reported on by The Globe.
Welcome Corps is geared to fast-track refugees, many of whom have waited years to be resettled. The goal is to welcome 5,000 refugees to the U.S. this year, the first to arrive as early as April.
Incidents reported the evening of Jan. 31 through the evening on Feb. 3.
Robert and Kelli Bush are scheduled to make their initial court appearances Feb. 7.