Worthington engineering work starting Monday

WORTHINGTON -- Work on the excavation of the flood retention area on CD 12 (west of Shopko) north of Ryan's Road is tentatively scheduled to begin as early as Monday.Ryan's Road will be open during the project; however, trucks will be hauling on ...

WORTHINGTON - Work on the excavation of the flood retention area on CD 12 (west of Shopko) north of Ryan’s Road is tentatively scheduled to begin as early as Monday.

Ryan’s Road will be open during the project; however, trucks will be hauling on Ryan’s Road. Traffic lanes were to be shifted as early as Thursday near the work site to allow for trucks to enter and exit the construction site from Ryan’s Road.

 

Weather permitting and construction proceeding as planned, construction of the retention area is expected to be completed in early November.

 

ADVERTISEMENT

Work on the replacement of the culvert on CD 12 under Oxford Street just west of Marine Avenue is also expected to begin the week of July 9. Through traffic on Oxford Street will be maintained during the culvert replacement. Traffic will be reduced to two lanes and shifted to the south during replacement of the north half of the culvert and shifted to the north during the replacement of the south half of the culvert.

 

This work is also expected to last until early November. Work on the Oslo Street culvert is not expected to begin until later in July.

What To Read Next
“Let’s put this in the rearview mirror,” Sen. Michael Diedrich, a Rapid City Republican said.
A resolution looking to allow the legislature to consider work requirements on the newly expanded Medicaid program is one step closer to the 2024 ballot.
Navigator CO2 Ventures is hoping to streamline the application process in Illinois as they add an additional pipeline to the mix.
The North Dakota Highway Patrol is investigating the Wednesday, Jan. 25, crash.